Construction of Flood Mitigation Structure, Barangay Sua, Canaman, Camarines Sur
Location
Sua, Canaman, Camarines Sur
Bicol Region
ZIP: 4401
13.620452, 123.135872
Project Cost
₱4.9M
₱4,897,900.0
Project Timeline
Start Date
February 21, 2024
Wed, Feb 21, 2024
Actual Start
February 21, 2024
Wed, Feb 21, 2024
Target Completion
April 17, 2024
Wed, Apr 17, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates